Our Indicative project programme
Environmental Surveys
From Q4 2024 till Q3 2025
Planning Application Preparation
From Q2 2025 till Q3 2025
Community Consultation
Q3 2025
Planning Submission
Early Q4 2025
Planning Determination Period
From Q1 2026 till Q2 2026
Discharge of Conditions
From Q3 2026 till Q4 2026
Ready to build
From Q1 2027
Construction and subsequent energisation to be determined post-completion of UK Grid Reform process.